Auckland International Airport needed a new taxiway to accommodate the Airbus A380 aircraft, as well as reduce aircraft congestion and delays and improve safety at times of low visibility.

Once constructed, this 600m-long 60m-wide taxiway doubled aircraft access from the busy international terminal to the main runway.

Using Fulton Hogan’s multi-disciplinary engineering capabilities, the runway has 20km of electrical ducts, 6km of subsoil drainage, 1km of concrete pipes and 53 airfield lights running through it. The most complex aspect was the tie-in sections of the taxiway programmed during set shutdowns over a six-week period.

Taxiway Lima was constructed over a nine-month period, using 50,000 tonnes of recycled concrete and 15,500 tonnes of asphalt. This approach had several significant benefits, with reduced demand for raw material, lower cost to the client, and less impact on the environment.

Taxiway Lima was the first of a network of taxiways serving the airport’s northern runway.

SHARE
LOCATION Auckland International Airport CLIENT Auckland International Airport Ltd VALUE NZ$15.5m START October 2012 END June 2013 CAPABILITY Airports Construction

You might also like...

Dunedin Airport – Gate 5 Extension

Dunedin Airport – Gate 5 Extension

  • SECTOR: Airports
  • LOCATION: Dunedin

We are extending the existing apron to allow for increased aircraft capacity at Dunedin Airport. Part of this work includes the replacement of existing stormwater...

READ MORE
Wellington International Airport Taxiway A Widening & Surfacing

Wellington International Airport Taxiway A Widening & Surfacing

  • SECTOR: Airports, Construction
  • LOCATION: Wellington

Recycling was an important focus during our work on the widening and resurfacing of Taxiway A at Wellington International Airport. We recycled 15 per cent...

READ MORE
Whitsunday Coast Airport Runway Upgrade

Whitsunday Coast Airport Runway Upgrade

  • SECTOR: Airports, Construction, Surfacing
  • LOCATION: Whitsunday

Whitsunday Coast Airport was the first project in Australia to achieve a zero waste status thanks to the innovative approach adopted by Fulton Hogan and...

READ MORE
Adelaide Airport T2 Apron & Taxiway Overlay

Adelaide Airport T2 Apron & Taxiway Overlay

  • SECTOR: Airports, Construction, Surfacing
  • LOCATION: Adelaide

Due to Adelaide’s hot climate, aircraft-induced shear stresses can push asphalt stability to its limits, resulting in severe deformation of runway and taxiway surfaces as...

READ MORE
National Aircraft Pavement Maintenance Programme 2014 – 2020

National Aircraft Pavement Maintenance Programme 2014 – 2020

  • SECTOR: Defence, Airports, Construction, Asset Management
  • LOCATION: Australia

Following the successful completion of projects under the 2011-14 Maintenance Works Contract, Fulton Hogan was re-engaged by the Department of Defence to perform various critical...

READ MORE