Te Ara Ihutai Christchurch Coastal Pathway

Client: Christchurch City Council
Duration: November 2021 – December 2023

Scope of Works:
Separable Portion 1 – Western pathway works (build only)

These works included construction of new rock revetment, pathway and a 4m asphalt path, some roading works (pedestrian crossing island and intersection modifications), demolition of an existing stone wall and construction/widening of an existing bridge structure.

Separable Portion 2 – Relocation and realignment of water and wastewater reticulation (design and build)

These works included design of and relocation/diversion of water and wastewater services to enable further structural elements and removal, replacement and abandonment of certain mains.

Separable Portion 3 – Realignment of Orion services and communication services reticulation (build only)

These works involved co-ordination with Orion and Connetics, provision of trenching for the diversion of cables, backfilling and temporary surface. restoration

Separable Portion 4 – Central and eastern pathway works (build only)

Construction of new rock revetment or anchorblock wall and a 4m path, some roading works (pedestrian crossing and intersection modifications), demolition and rebuild of existing wall, car park works (kerbs, landscaping and surfacing), in-road works (elements of car park works and new pedestrian crossing island) and service relocations near bend where services clash with anchorblock tie backs.

From Boat Sheds to Shag Rock (from the 740m mark to the 1,100m mark):

Construction of a new structure and 4m path, large in situ concrete foundation and concrete panels forming the path, pre-cast f-type barrier to separate path from road and some roading works (construction of a pedestrian crossing island).

Copy LinkEmailTwitterLinkedIn

You might also like...

Lifting our national game on water infrastructure

Lifting our national game on water infrastructure

  • LOCATION: New Zealand

New Zealand is approaching the start of the first great water infrastructure renewal cycle in our history. Older countries, such as those in Europe, America,...

READ MORE
NCI Project Nears Completion With A Flourish

NCI Project Nears Completion With A Flourish

  • LOCATION: Auckland

One of the final touches on the five-year Northern Corridor Improvements (NCI) project has also proved to be one of the more dramatic. A 30...

READ MORE
New Waikato asphalt plant a sign of the future

New Waikato asphalt plant a sign of the future

  • LOCATION: Waikato

The first of Fulton Hogan’s four new Marini 2500 batch asphalt plants has been commissioned in the Waikato, as part of a major enhancement of...

READ MORE