Waimea Community Dam all set

1 March 2024:

The Waimea Community Dam has had its final concrete pour – a 91m3, five-and-a-half hour effort this week, involving 10 concrete trucks.

The pre-dawn concrete pour created a mass block and end wall for the valves that control the water flow from the dam’s reservoir – Te Kurawai o Pūhanga – into the Lee River.

Over recent weeks the Lee River has been fed via the spillway while the temporary HDPE pipe that diverted the river was removed, and the dam’s pipework and systems installed.  The flow over the spillway can be seen to the right of the image.

Engineering analysis and verification of dam performance is due to be completed shortly by Waimea Water Ltd.

The Waimea Community Dam has been built for Waimea Water Ltd by Fulton Hogan and Taylors Contracting. It is the first large dam to be constructed in New Zealand in 25 years and the first publicly-funded large dam to be constructed since the Clyde Dam was finished 30 years ago.

 

 

Copy LinkEmailTwitterLinkedIn

You might also like...

Stevenson drives science-backed approach to safety bunds in quarries

Stevenson drives science-backed approach to safety bunds in quarries

Originally published by Stevenson on 13 November 2024 Our journey...

Read More
Key milestone for Te Mārua Water Treatment Plant

Key milestone for Te Mārua Water Treatment Plant

6 November 2024: The Te Mārua Water Treatment Plant Optimisation...

Read More
New asphalt plant lifts capacity, lowers CO2 emissions

New asphalt plant lifts capacity, lowers CO2 emissions

5 November 2024: The second of Fulton Hogan’s four new...

Read More